If your business electricity bill has a demand charge measured in kVA, your power factor affects what you pay. A site with poor power factor draws more from the network than it uses for work, and the network charges for the difference. This guide explains power factor in plain terms, where it shows up in South Australian network tariffs, and what correction involves.
What is power factor?
Power factor is the ratio of real (working) power to apparent (total) power (US Department of Energy). There are three quantities to keep in mind:
- Real power, in kilowatts (kW). The power that does the work: turning a motor shaft, heating, lighting.
- Reactive power, in kilovars (kVAr). The non-working power that inductive equipment needs to create its magnetic field.
- Apparent power, in kilovolt-amps (kVA). The total the supply has to deliver, made up of the real and reactive power together.
Power factor is kW divided by kVA. The Department of Energy’s example is a load of 100 kW that also needs 100 kVAr of reactive power. The apparent power is 142 kVA, so the power factor is 100 divided by 142, or about 0.70. Only 70% of the current supplied is doing useful work.
What causes low power factor?
Inductive loads. The Department of Energy lists transformers, electric motors and high-intensity discharge lighting, which make up a large share of the load in industrial sites. Its motor systems fact sheet adds that low power factor results when induction motors run at less than full load, and that oversized or underloaded motors lead to low power factor (US Department of Energy).
So if your site runs a lot of motors, such as a factory, a pumping station or a processing plant, power factor is worth checking.
Why does low power factor cost SA businesses money?
Because some network tariffs charge for demand in kVA, and a lower power factor means more kVA for the same work.
SA Power Networks sets the network tariffs it charges to distribute electricity. Its small and medium business page says its medium business demand tariff is based on the highest power usage in a 30-minute interval over the last 12 months, and that the tariff is based on the kVA demand a customer places on the network. That tariff applies to business customers using between 40,000 and 160,000 kWh a year with demand above 120 kVA (SA Power Networks).
SA Power Networks also has large LV and HV business tariffs. In its Tariff Price List for 2026 to 2027, the demand rates for those tariffs are set in dollars per kVA per day.
The price list also includes power factor excess kVAr charges. It says customers must comply with the power factor requirements of the South Australian Distribution Code, and that an annual charge is applied if an installation isn’t compliant at times of its monthly peak demand.
Here is why power factor matters on a kVA tariff. Using the Department of Energy’s example, a 100 kW load at a power factor of 0.70 draws 142 kVA. Raise the power factor to 0.95 and the same 100 kW draws about 105 kVA. The work done is the same, but the demand the network measures is about a quarter lower.
What does power factor correction involve?
The Department of Energy lists four ways to improve power factor:
- minimise the operation of idling or lightly loaded motors
- avoid running equipment above its rated voltage
- replace standard motors with energy-efficient motors as they fail, and run motors near their rated capacity
- install capacitors to reduce the reactive power
Capacitors work against the inductive load. The Department of Energy explains that they release energy that opposes the reactive energy of the inductive equipment, which reduces the current that has to come from the supply. They can be fitted at individual motors or at the motor control centre. The City of Newcastle describes its units the same way: capacitors that balance out inductive loads such as motors, lifts and air conditioners.
A real example. The City of Newcastle in NSW fitted power factor correction units at three council sites. At Lambton Pool, a 100 kVAr unit lifted the average power factor from 0.81 to 0.99 and cut annual demand from 206 kVA to 168.5 kVA (City of Newcastle). Results depend on the site and the tariff, so treat that as an illustration, not a forecast.
How do you know if your site needs it?
- Check your bill. Look for a demand charge in kVA, or an excess kVAr or power factor charge.
- Get the data. Your metering data shows your peak demand. A site survey with a power quality logger shows your power factor through the day.
- Size it properly. The correction needed depends on the load profile, so equipment should be sized from measured data. The Department of Energy recommends getting help to work out the right amount of correction and where to install it.
- Plan the installation. Fitting correction equipment is electrical work. In SA that means a licensed electrical contractor, with the work done by a registered electrician (SA.GOV.AU).
Where VD fits
VD Fire & Electrical’s engineering line designs power distribution for commercial and industrial sites across Adelaide, surveys and upgrades older installations, and can add monitoring so you can see how the site is running. Electrical installation work is carried out through our licensed electrical contractor. If power factor is on your bill, tell us about the site and we’ll say plainly whether we can help as part of a design or upgrade. See electrical design and installation, or read what SCADA is if you’re also looking at monitoring and control.