Based in Enfield. Working across Adelaide and regional SA. 08 8151 1040

Bushfire overlays and Bushfire Attack Levels (BAL) in South Australia

South Australia's Planning and Design Code has six bushfire hazard overlays, High Risk, Medium Risk, General Risk, Urban Interface, Regional and Outback, and some land sits outside all of them. The overlay decides which bushfire planning rules apply, and under SA's version of the building code it also sets the Bushfire Attack Level (BAL), with High Risk sites assessed individually under AS 3959.

If you’re buying, building or extending in the Adelaide Hills or on the city fringe, sooner or later someone will ask which bushfire overlay applies and what your BAL is. The two are linked: the overlay comes from the state planning rules, and in most cases it sets the BAL your building has to meet.

What are the bushfire hazard overlays in the Planning and Design Code?

The Planning and Design Code is the single planning rulebook for South Australia. It applies overlays to land, and six of them deal with bushfire hazard: High Risk, Medium Risk, General Risk, Urban Interface, Regional and Outback. The CFS says these overlays “determine whether you need approval and which policies apply to your address” (CFS, Building and renovating in a bushfire prone area, updated August 2026).

SA.GOV.AU splits them into two groups:

  • Designated bushfire prone areas: General Risk, Medium Risk, High Risk, and Urban Interface within 500 m of High Risk land.
  • Other bushfire protection areas, which are not designated bushfire prone but still need protecting from bushfire: Outback, Regional and Urban Interface.

Planning requirements in these areas can include referral to a fire service, dedicated water supplies for firefighting, buffer zones between homes and flammable vegetation, and suitable access roads.

How does the overlay set your BAL?

South Australia’s variation to the National Construction Code (NCC 2022 clause SA H7D4 for houses and sheds, and SA G5D5 for other buildings) ties the Bushfire Attack Level to the overlay (ABCB, NCC 2022 Volume Two, South Australia). In a designated bushfire prone area:

Overlay Bushfire Attack Level
General Risk BAL-Low
Medium Risk BAL-12.5
High Risk Assessed for the site under AS 3959
Urban Interface within 500 m of High Risk BAL-Low
Urban Interface within 100 m of High Risk Assessed for the site under AS 3959

This is the NCC 2022 wording. Building rules are updated from time to time, so your building surveyor will confirm the edition that applies when you lodge.

What is a Bushfire Attack Level?

The CFS describes a BAL as a way of measuring how severely a building could be exposed to ember attack, radiant heat and direct flame contact. It is measured in radiant heat, in kilowatts per square metre, as defined by Australian Standard AS 3959:2018. AS 3959 sets the assessment method, using the vegetation type, the distance from the site to the vegetation and the slope of the land under it. It also sets the construction materials for each level.

There are six levels: BAL-LOW, BAL-12.5, BAL-19, BAL-29, BAL-40 and BAL-FZ (Flame Zone). The number is the maximum radiant heat, so BAL-19 means up to 19 kW/m². The CFS says BAL-LOW is the lowest risk and has no additional construction requirements, while BAL-40 and BAL-FZ are very high to extreme risk and need significant, specialist construction.

When do you need a BAL assessment in SA?

The CFS’s planning and building FAQs cover the common cases:

  • High Risk overlay. Your development application is referred to the CFS for comment and a BAL assessment. The CFS looks at site access, vegetation within 100 m of the development, and firefighting water supply and equipment.
  • Urban Interface with High Risk land within 100 m. You may need a BAL assessment, and you arrange it directly with the CFS because council won’t refer it.
  • A shed under 500 m² within 6 m of a home. The CFS says this needs a BAL assessment, because the shed must be built to the same bushfire rating as the home.
  • Changing the plans. Moving the house, changing its size or changing the layout can change the BAL. An approval is only valid for the plans that were assessed.

In the High Risk overlay, the CFS report can also set water supply requirements under Ministerial Building Standard MBS 008. The CFS says tanks for bushfire safety must be non-combustible, and where a pump is needed it must be a 5 horsepower (3.7 kW) fuel-driven pump that works independently of mains power.

How do you check your property’s bushfire overlay?

  1. Search your address in the Planning and Design Code’s property lookup. This is the page the CFS points to for checking your bushfire hazard rating.
  2. Or use the SA Property and Planning Atlas (SAPPA), which SA.GOV.AU links for viewing the Code’s overlays on a map.
  3. For a development question, contact the CFS Development Assessment Service on 08 8115 3372 or das@cfs.sa.gov.au. For a property you already own, the CFS suggests your council’s Fire Prevention Officer.

Which Adelaide suburbs have the most High Risk overlay?

Our area pages show how much of each suburb sits in each overlay. We measured PlanSA’s Planning and Design Code overlay dataset (August 2026 release) against ABS 2021 suburb boundaries. These are some of the suburbs with the largest High Risk shares:

Suburb Council Share in the High Risk overlay
Mount Osmond Burnside 100%
Upper Sturt Adelaide Hills 100%
Kersbrook Adelaide Hills 100%
One Tree Hill Playford 100%
Belair Mitcham 94%
Eden Hills Mitcham 93%
Hahndorf Mount Barker 92%
Coromandel Valley Onkaparinga 91%
Happy Valley Onkaparinga 78%
Flagstaff Hill Onkaparinga 73%
Crafers Adelaide Hills 72%
Stirling Adelaide Hills 55%

The rest of the picture varies a lot. Victor Harbor has no High Risk land but 48% Medium Risk. Kadina is almost entirely Regional. Plains suburbs such as Enfield sit outside every bushfire overlay.

A suburb share is a guide only. Your property can be in a different overlay from most of its suburb, and overlays change through Code Amendments, so always check your own address.

What this means for building owners

A BAL is about how a building is constructed. It doesn’t replace the everyday duties that come with owning land in SA: every owner of private land must take reasonable steps to prevent fire starting or spreading and to protect life and property (Fire and Emergency Services Act 2005, section 105F). Commercial buildings in any overlay still need their fire safety equipment maintained. Our bushfire preparation guide for businesses covers the season itself, and the Fire Danger Season guide has this year’s dates.

BAL assessments are a job for the CFS or a private assessor. VD Fire & Electrical services the extinguishers and fire hose reels on commercial sites across Adelaide and the Hills, and your first fire safety audit is free. See our fire safety inspections or call 08 8151 1040.

Frequently asked questions

Does the Urban Interface overlay mean I need a BAL assessment?
Only near High Risk land. Under SA's variation to the National Construction Code, Urban Interface land within 100 m of a high bushfire risk area is assessed under AS 3959, and Urban Interface land within 500 m gets BAL-Low (ABCB). The CFS says council won't refer these applications, so you arrange the assessment directly with the CFS.
Who does BAL assessments in South Australia?
When a development application in the High Risk overlay is referred to the CFS, its Development Assessment Service assesses it. The CFS says that if you only need a BAL, for example when replacing a window or roof, you will need to use a private provider.
Can I reduce my property's BAL?
Sometimes. The CFS says you may be able to reduce vegetation or move the building further away from it, but only vegetation inside your own boundary counts, and the assessment looks at vegetation within 100 m. Don't clear anything before you have development approval or native vegetation approval.
Is SA changing its bushfire overlays?
A state-wide update to the bushfire parts of the Code has been out for public consultation. The CFS guide, updated August 2026, says it would cut the number of overlays to three and that there is no planned commencement date (CFS).
How much does a CFS BAL assessment cost?
The CFS says fees for statutory referrals and services such as on-site BAL assessments are set under the Planning, Development and Infrastructure Act and the Fire and Emergency Services Act, and updated each year in the Government Gazette. For residential referrals, the CFS has 30 business days to respond.

Book your next service

Tell us what's on site and we'll send a fixed price the same day.

Call 08 8151 1040 Get a quote